All applications for solar panel projects should be submitted to the EAC (Electricity Authority of Cyprus).
One of the initial meter replacement charges involves the meter. It will be replaced by a bidirectional system (it records twice) which records the energy produced by solar panels.
After you submit your application, you will usually receive the decision (approval/rejection) from EAC within 7 working days.
If the EAC rejects your application, the administration fee of 50 euros will be retained, but you will be refunded the remaining 200 euros plus VAT for the meter replacement.
If your application is successful, you will need to request an inspection by and a connection to the EAC. They will complete the inspection and connection within 25 working days.
It is also important to understand that inspection, connection and installation should be completed within 60 working days. The first day counts from the date of your solar panel application. If these three steps are not completed within the deadline, your approval will no longer be valid.